26th April 2019

Latest Update The West Newton A-2 appraisal well, targeting the Kirkham Abbey Shoal and Cadeby Reef formations, was spud at 01:45am on Friday 26 April 2019. Rathlin Energy (UK) Limited is the well operator and has a working interest of 66.67% in PEDL183. The well will be drilled to a total depth of approximately 2,061 metres below ground level. This phase of operations is expected to take approximately eight weeks to complete.     12th April 2019 This week, Rathlin Energy (UK) Limited mobilised the drilling rig and associated equipment to the West Newton site. As of 13 April 2019,…

Read More
UPDATE: West Newton A site
4th December 2018